Waterfall Project Management Method -CSI schedule

10/20/202315 min read

person holding black android smartphone
person holding black android smartphone

Developing a schedule for a 6-story wood frame hotel requires careful planning and coordination of various tasks. The waterfall project management method is a sequential approach that involves completing each phase before moving on to the next. This method is particularly useful for construction projects as it allows for a systematic and organized approach to scheduling.

The first step in developing the schedule is to identify the project tasks. The CSI Master Division tasks provide a comprehensive framework for organizing these tasks. This framework categorizes the various activities involved in hotel construction into different divisions such as site preparation, concrete, masonry, metals, and so on. By using this framework, it becomes easier to break down the project into smaller, manageable tasks.

Once the tasks have been identified, the next step is to determine their sequence. This involves understanding the dependencies between tasks and determining the order in which they need to be completed. For example, before the concrete foundation can be poured, the site preparation tasks such as excavation and grading need to be completed. By identifying these dependencies, it becomes possible to create a logical sequence of tasks.

After determining the task sequence, the next step is to estimate the duration of each task. This involves considering factors such as the complexity of the task, the availability of resources, and any potential risks or delays. It is important to be realistic when estimating the duration of tasks to ensure that the schedule is achievable and accurate.

Once the task durations have been estimated, the next step is to assign resources to each task. This involves identifying the specific individuals or teams responsible for completing each task and allocating the necessary resources such as labor, equipment, and materials. By assigning resources to tasks, it becomes possible to identify any potential resource constraints or conflicts and make adjustments accordingly.

With the task sequence, duration, and resources determined, the next step is to create a Gantt chart using Microsoft Project or a similar scheduling software. A Gantt chart is a visual representation of the project schedule that shows the start and end dates of each task, as well as any dependencies or constraints. This chart provides a clear and concise overview of the project timeline and allows for easy monitoring and tracking of progress.

Once the schedule has been developed, it is important to regularly review and update it throughout the course of the project. This involves monitoring the progress of tasks, identifying any delays or issues, and making necessary adjustments to ensure that the project stays on track. Regular communication and collaboration with the project team are essential for maintaining an accurate and up-to-date schedule.

In conclusion, developing a schedule for a 6-story wood frame hotel requires careful planning, coordination, and attention to detail. By following the waterfall project management method and using the CSI Master Division tasks as a framework, it becomes possible to create a comprehensive and accurate schedule. Regular monitoring and updating of the schedule are essential for ensuring the successful completion of the project.

Understanding the Waterfall Project Management Method

The waterfall project management method is a sequential approach to managing projects. It follows a linear progression, where each phase of the project is completed before moving on to the next. This method is often used in construction projects, where tasks need to be completed in a specific order.

When developing a schedule using the waterfall method, it is important to break down the project into smaller tasks and define the dependencies between them. This allows for a clear understanding of the project timeline and helps in identifying any potential bottlenecks or delays.

In the waterfall method, the project is divided into distinct phases, such as initiation, planning, execution, monitoring, and closure. Each phase has its own set of deliverables and milestones that need to be achieved before progressing to the next phase. This ensures that there is a systematic approach to project management and that each phase is completed before moving on to the next.

One of the advantages of the waterfall method is that it provides a clear structure for project management. By following a sequential approach, it becomes easier to plan and allocate resources, as well as track progress. This method also allows for better documentation, as each phase has its own set of deliverables that need to be completed and signed off on.

However, the waterfall method also has its limitations. One of the main drawbacks is that it does not allow for much flexibility or adaptability. Once a phase is completed, it is difficult to make changes or go back to a previous phase. This can be problematic if there are changes in requirements or if issues arise during the project. Additionally, the waterfall method does not encourage collaboration or feedback between team members, as each phase is completed before moving on to the next.

In conclusion, the waterfall project management method is a sequential approach to managing projects that is often used in construction projects. It provides a clear structure for project management and allows for better documentation. However, it lacks flexibility and adaptability, which can be problematic in certain situations. It is important to carefully consider the nature of the project and its requirements before deciding to use the waterfall method.

For Division 02 - Existing Conditions, the subdivision of tasks may include conducting site surveys and investigations to assess the existing conditions of the site. This could involve analyzing soil samples, evaluating the stability of existing structures, and identifying any potential hazards or limitations that may impact the construction process. Additionally, tasks related to the demolition and removal of existing structures or infrastructure may be included in this division.

In Division 03 - Concrete, the subdivision of tasks may involve the preparation and pouring of concrete foundations, slabs, and structural elements. This could include tasks such as excavation, formwork, reinforcement installation, concrete placement, and curing. Quality control and testing of the concrete may also be included in this division to ensure that the specified strength and durability requirements are met.

For Division 04 - Masonry, the subdivision of tasks may include the construction of masonry walls, partitions, and finishes. This could involve tasks such as laying bricks or blocks, applying mortar, and finishing the surfaces to achieve the desired aesthetic appearance. Additionally, tasks related to the installation of masonry reinforcements, such as steel bars or wire mesh, may also be included in this division.

In Division 06 - Wood, Plastics, and Composites, the subdivision of tasks may encompass the installation of wood framing, finishes, and millwork. This could include tasks such as framing walls, floors, and roofs using wood or engineered wood products. The installation of interior finishes, such as doors, trim, and cabinetry, may also be included in this division. Additionally, tasks related to the installation of plastic or composite materials, such as vinyl siding or composite decking, may also be part of this division.

For Division 07 - Thermal and Moisture Protection, the subdivision of tasks may involve the installation of insulation, roofing, and waterproofing systems. This could include tasks such as installing insulation materials to improve energy efficiency, applying roofing membranes or shingles to protect against water infiltration, and installing waterproofing membranes or coatings to prevent moisture penetration. Additionally, tasks related to the installation of vapor barriers or air barriers may also be included in this division.

In Division 08 - Openings, the subdivision of tasks may include the installation of doors, windows, and glazing systems. This could involve tasks such as framing openings, installing door and window frames, and fitting glass or other glazing materials. Additionally, tasks related to the installation of hardware, such as locks or hinges, may also be included in this division.

By organizing the project according to the CSI Master Division tasks, we can ensure that all necessary tasks are identified and accounted for in the project schedule. This helps to streamline the construction process, improve coordination between different trades, and facilitate effective communication among project stakeholders. It also provides a standardized framework that allows for easy reference and comparison across different construction projects.

Division 02 - Existing Conditions

The purpose of this division is to prepare the site and address any existing conditions that may affect the construction process. The subdivision of tasks for Division 02 may include:

  • Site survey and assessment

  • Demolition of existing structures

  • Excavation and earthwork

  • Utility connections and relocations

  • Environmental assessment and remediation

  • Geotechnical investigations

  • Structural assessment and repairs

  • Architectural assessment and renovations

  • Historical preservation and restoration

  • Landscaping and site improvements

  • Permitting and regulatory compliance

Site survey and assessment involves conducting a comprehensive survey of the site to gather data on existing features, such as topography, boundaries, and utilities. This information is crucial for accurate planning and design of the construction project.

Demolition of existing structures may be necessary to clear the site and make way for new construction. This can involve the removal of buildings, foundations, and other structures that are no longer needed or are in poor condition.

Excavation and earthwork are essential for preparing the site for construction. This includes digging trenches, grading the land, and removing any excess soil or debris. Proper excavation ensures a solid foundation for the new structures.

Utility connections and relocations involve coordinating with utility companies to establish or relocate connections for water, electricity, gas, and other services. This ensures that the site has the necessary infrastructure to support the construction project.

Environmental assessment and remediation are important to identify and address any potential environmental hazards or concerns on the site. This may involve testing soil and water samples, removing hazardous materials, or implementing measures to protect the surrounding environment.

Geotechnical investigations are conducted to understand the soil and rock conditions at the site. This information helps engineers and designers determine the appropriate foundation design and construction methods to ensure the stability and safety of the structures.

Structural assessment and repairs may be necessary for existing buildings or structures that are being retained as part of the construction project. This involves evaluating the condition of the structures and making any necessary repairs or reinforcements to ensure their integrity.

Architectural assessment and renovations may be required for historical or heritage buildings that are being preserved or restored. This involves working with architects and preservation experts to assess the condition of the buildings and develop plans for their renovation or restoration.

Historical preservation and restoration are important for maintaining the cultural and historical significance of certain structures. This may involve preserving original features, restoring damaged elements, and using appropriate materials and techniques to ensure authenticity.

Landscaping and site improvements are essential for creating an aesthetically pleasing and functional environment. This includes designing and implementing landscaping features, such as gardens, pathways, and outdoor spaces, to enhance the overall appeal of the site.

Permitting and regulatory compliance involve obtaining the necessary permits and approvals from local authorities and ensuring compliance with relevant regulations and codes. This ensures that the construction project meets all legal requirements and standards.

In summary, Division 02 - Existing Conditions encompasses a wide range of tasks and activities aimed at preparing the site and addressing any existing conditions that may impact the construction process. By carefully assessing and addressing these conditions, the construction project can proceed smoothly and efficiently, laying the groundwork for successful completion.

Foundation design and excavation is a crucial aspect of Division 03. It involves determining the appropriate foundation type for the hotel based on factors such as soil conditions, building loads, and local building codes. The excavation process includes digging trenches and pits to prepare the site for the foundation construction. This may also involve the removal of any existing structures or debris that may hinder the construction process.

Formwork and reinforcement are essential components of Division 03. Formwork refers to the temporary structures that are used to shape and support the concrete during the pouring and curing process. It ensures that the concrete takes the desired shape and remains in place until it hardens. Reinforcement involves the placement of steel bars or mesh within the formwork to provide additional strength and stability to the concrete structure.

Pouring and curing of concrete is a critical step in Division 03. Once the formwork is in place and the reinforcement is properly positioned, the concrete is poured into the designated areas. This requires careful coordination and precision to ensure that the concrete is evenly distributed and free from any air pockets or voids. After pouring, the concrete needs to be cured properly to develop its full strength and durability. This typically involves maintaining the right temperature and moisture levels for a specific period.

Structural inspections are an integral part of Division 03. These inspections are conducted at various stages of the concrete construction process to ensure that the work is being carried out in compliance with the approved plans and specifications. Inspectors check for any potential defects or issues that may compromise the structural integrity of the hotel. They also verify that the concrete meets the required strength and quality standards.

In conclusion, Division 03 - Concrete plays a vital role in establishing the solid foundation and structural elements of the hotel. It encompasses tasks such as foundation design and excavation, formwork and reinforcement, pouring and curing of concrete, and structural inspections. Each of these tasks requires careful planning, coordination, and adherence to industry standards to ensure the successful construction of a durable and safe hotel.

Division 04 - Masonry

The purpose of this division is to construct the masonry walls and partitions of the hotel. Masonry work is an essential component of the overall construction process, as it provides structural integrity, aesthetic appeal, and durability to the building. The subdivision of tasks for Division 04 may include:

  • Masonry wall layout and design: This involves carefully planning the placement of masonry walls and partitions according to the architectural drawings and specifications. It requires a thorough understanding of building codes, structural requirements, and design principles to ensure that the walls are properly aligned and positioned.

  • Brick or block installation: Once the layout and design are finalized, the actual installation of bricks or blocks can begin. This task requires skilled masons who have expertise in handling different types of masonry units. They must carefully lay each unit, ensuring proper alignment, levelness, and plumpness to create a solid and visually pleasing wall.

  • Mortar mixing and application: Mortar is a crucial component in masonry construction as it acts as the bonding agent that holds the bricks or blocks together. Masons must carefully mix the mortar, following the specified proportions of cement, sand, and water. They then apply the mortar to the joints between the masonry units, ensuring a strong and durable bond.

  • Finishing and cleaning of masonry surfaces: Once the masonry walls are constructed, they require finishing touches to enhance their appearance. This may involve techniques such as pointing, where the mortar joints are shaped and smoothed, or applying a special finish to achieve a desired texture or color. Additionally, masons must clean the masonry surfaces, removing any excess mortar, dirt, or stains to ensure a clean and polished final result.

Overall, Division 04 plays a crucial role in the successful completion of the hotel construction project. The skilled masons and their attention to detail ensure that the masonry walls and partitions are not only structurally sound but also visually appealing, contributing to the overall aesthetic of the building.

Division 06 - Wood, Plastics, and Composites

The purpose of this division is to install the wood framing, finishes, and millwork of the hotel. The subdivision of tasks for Division 06 may include:

  • Wood framing design and layout

  • Installation of wall studs and roof trusses

  • Installation of interior finishes and millwork

  • Quality control and inspections

  • Wood preservation and treatment

  • Installation of wood paneling and siding

  • Installation of wood flooring and decking

  • Installation of wood doors, windows, and cabinetry

  • Installation of wood trim and molding

  • Installation of plastic and composite materials

Wood preservation and treatment is an important aspect of Division 06. It involves the application of various treatments to protect the wood from decay, insects, and other forms of damage. This may include the use of preservatives, sealants, and coatings to ensure the longevity and durability of the wood materials used in the hotel construction. In addition to wood, Division 06 also encompasses the installation of other materials such as plastic and composite materials. These materials are often used in applications where their properties, such as resistance to moisture or fire, make them more suitable than traditional wood. Plastic and composite materials may be used in the construction of exterior facades, decking, and other areas where durability and low maintenance are desired. The installation of wood paneling and siding is another important task within Division 06. This involves the careful placement and attachment of panels or individual boards to create a visually appealing and functional surface. Wood paneling and siding can enhance the aesthetic appeal of the hotel, providing warmth and character to the interior and exterior spaces. Wood flooring and decking installation is also included in Division 06. This task involves the proper laying and finishing of wood flooring and decking materials to create a smooth and even surface. Wood flooring adds a touch of elegance and sophistication to the hotel's interior spaces, while wood decking provides a comfortable and inviting outdoor area for guests to enjoy. The installation of wood doors, windows, and cabinetry is an essential part of Division 06. These elements not only serve functional purposes but also contribute to the overall design and ambiance of the hotel. Wood doors and windows can provide insulation and security, while wood cabinetry adds storage and organization to the hotel's rooms and common areas. Wood trim and molding installation is another aspect of Division 06. This task involves the careful placement and attachment of decorative elements such as crown molding, baseboards, and trim around doors and windows. Wood trim and molding can add a finishing touch to the hotel's interior spaces, creating a polished and refined look. In conclusion, Division 06 encompasses a wide range of tasks related to the installation of wood, plastics, and composites in the hotel construction. From wood framing and finishes to the installation of plastic and composite materials, each task plays a crucial role in creating a high-quality and visually appealing hotel environment. Quality control and inspections ensure that all work is done to the highest standards, resulting in a hotel that is not only aesthetically pleasing but also durable and long-lasting.

Division 07 - Thermal and Moisture Protection

The purpose of this division is to ensure that the hotel is protected from thermal and moisture-related issues. This division plays a crucial role in maintaining the structural integrity and longevity of the building. The subdivision of tasks for Division 07 encompasses various aspects of thermal and moisture protection, including:

  • Installation of insulation materials: Insulation is a key component in preventing heat loss or gain, thus ensuring energy efficiency and occupant comfort. This task involves the selection and installation of appropriate insulation materials, such as fiberglass, foam, or cellulose, in walls, floors, and roofs. The installation process must adhere to industry standards and local building codes.

  • Roofing installation and waterproofing: The roof is one of the most critical elements in protecting the hotel from moisture infiltration. Proper roofing installation involves the selection of suitable materials, such as asphalt shingles, metal panels, or membrane systems, and their correct installation to ensure a watertight seal. Waterproofing measures, such as the application of waterproof membranes or coatings, are also implemented to safeguard against leaks and water damage.

  • Sealing of exterior openings: Exterior openings, such as windows, doors, and joints, can be potential entry points for moisture. Therefore, proper sealing techniques are employed to prevent water intrusion. This may include the use of weatherstripping, caulking, or flashing to create a barrier against moisture penetration.

  • Testing and verification of moisture protection: To ensure the effectiveness of the thermal and moisture protection measures, thorough testing and verification procedures are carried out. These may include moisture content analysis, infrared thermography, or air leakage tests to identify any potential weaknesses or areas of concern. This allows for timely remediation and ensures that the hotel remains adequately protected.

By addressing these tasks within Division 07, the hotel can mitigate the risks associated with thermal and moisture-related issues, enhancing the overall durability, energy efficiency, and comfort of the building.

Division 08 - Openings

The purpose of this division is to install doors, windows, and glazing systems in the hotel. These components play a crucial role in providing security, natural light, and ventilation to the building. The subdivision of tasks for Division 08 may include:

  • Door and window selection: This involves carefully choosing the appropriate doors and windows based on factors such as design, functionality, energy efficiency, and compliance with building codes. The selection process may also consider factors like sound insulation, fire resistance, and accessibility requirements.

  • Installation of exterior and interior doors: Skilled craftsmen will be responsible for installing various types of doors, including entrance doors, fire-rated doors, sliding doors, and interior doors. They will ensure that the doors are properly aligned, operate smoothly, and provide a secure seal.

  • Glazing and sealing of windows: This task involves the installation of glass panes into window frames, ensuring that they are properly sealed to prevent air and water infiltration. Glazing options may include single, double, or triple glazing, depending on the desired level of insulation and sound reduction.

  • Hardware installation and finishing: Once the doors and windows are installed, the hardware such as locks, handles, hinges, and closers will be fitted. This step requires attention to detail to ensure that all components are properly aligned and functioning correctly. Finishing touches, such as painting or staining, may also be applied to enhance the aesthetics of the openings.

By organizing the project tasks according to these divisions and subdivisions, we can create a comprehensive schedule that covers all aspects of the construction process. This allows for efficient coordination between different trades and ensures that the openings are installed to the highest standards of quality and safety. Additionally, proper installation and sealing of doors and windows contribute to the overall energy efficiency of the building, reducing heating and cooling costs for the hotel. The Division 08 team will work closely with architects, engineers, and other stakeholders to ensure that the openings meet the design intent and functional requirements of the project.

Developing the Schedule using Microsoft Project

Once we have a clear understanding of the project tasks and their dependencies, we can use project management software like Microsoft Project to develop the schedule.

Microsoft Project allows us to create a visual representation of the project timeline, assign resources to tasks, and track progress. Here are the steps to develop the schedule using Microsoft Project:

  1. Create a new project in Microsoft Project and set the project start date.

  2. Enter the project tasks based on the CSI Master Division tasks and their subdivisions. Include task durations and dependencies.

  3. Assign resources to each task, such as the project manager, construction team, and subcontractors. This step is crucial as it ensures that each task has the necessary resources allocated to it, enabling a smooth workflow and preventing any delays in the project.

  4. Define any milestones or important deadlines in the project. Milestones are significant events or achievements that mark the completion of a phase or the entire project. These can include obtaining permits, completing foundation work, or finishing the interior design.

  5. Review the schedule for any conflicts or bottlenecks. Adjust task durations or dependencies as necessary. Microsoft Project provides tools to identify any conflicts or bottlenecks in the schedule, such as tasks that have overlapping timelines or resource overallocations. By resolving these issues, you can ensure a realistic and achievable schedule.

  6. Once the schedule is finalized, share it with the project team and stakeholders. Communication is key in any project, and sharing the schedule with the team and stakeholders ensures that everyone is aware of the project timeline and their respective responsibilities. This promotes collaboration and accountability.

  7. Regularly update the schedule as the project progresses and track the actual progress against the planned timeline. As the project unfolds, it is essential to keep the schedule up to date by recording the actual start and finish dates of tasks. This allows for accurate tracking of progress and enables timely adjustments to the schedule if needed.

By following these steps and using Microsoft Project, you can develop a detailed and accurate schedule for your 6-story wood frame hotel project. The software's features and capabilities provide the necessary tools to effectively plan and manage the project from start to finish. With a well-developed schedule in place, you can ensure that the project stays on track, resources are utilized efficiently, and deadlines are met.